Tuesday 1 September 2015

Crane Operator Multiple Choice Questions And Answers

11.  What should the operator do if communication is lost to the signal person? 
A. Continue with movement until told otherwise
B. Stop movement until communication is restored (Correct Answer)
C. Cable up until the load is in view
D. Get out of the machine and check on the load (Your Answer)
Ans: B

12.  How often must the communication between the signal person and operator be maintained during crane movements? 
A. Continuously (Correct Answer)
B. Daily
C. Hourly
D. Only while swinging  (Your Answer)
Ans: A

13.  Who can signal a crane to stop during a lift? 
A. Only the qualified signal person
B. The dedicated crane oiler
C. Anyone (Correct Answer)
D. Only the superintendent in charge of the operation (Your Answer)
Ans:C

14. When Operating a Crane, which of the following is not necessary to take into 
consideration? 
A. Soil Conditions
B. Time of Day
C. Proximity to Power Lines
D. Load Chart Specifications
Ans: B

15. It is critical to know the weight capacity of a crane before hoisting a load? 
A. True
B. False
Ans: A