6. Which Organization element are mandatory for Creation of the Project Definition in SAP PS ECC?
a. Controlling Area
b. Controlling Area and Company Code
c. Controlling Area and Plant
d. Controlling Area, Company Code and Proj Currency
Answer: a

7. Which of the following are possible user exits that can be used while processing materials from the Project Systems?
a.        CNEX0009 -- EXIT_SAPLCOMK_001
b.        CNEX0011 -- EXIT_SAPLCOMK_002
c.        CNEX0015 -- EXIT_SAPLCN10_002
d.        CN015AFZ -- EXIT_SAPLCNFZ_003
Answer: a, b, c

8. With reference to material requirements in Project System (PS-MAT), which of the following statements are true?
a. 9999 components may be created per network.
b. Project System supports consignment stock.
c. Component scrap is considered during BOM explosion.
Answer: A

9. Could a user with Access Control List (ACL) authorization ‘Read’ lock a project?
a.        Yes
b.        No
Answer: A

10. How many levels of WBS elements can be created in Project Systems module?
a. 999
b. 256
c. 99
d. 255
Answer: D