1. What is the use of item number in maintenance order?
Item number refers to the number (not material number) to identify the material component that is to be used for an operation in the maintenance order.It is generally given in increments of 0010.It is the first field in the Components tab of a maintenance order.

2. What is refurbishment order? Explain the total cycle?
Refurbishment order is used for upgradation of damaged / defective spare parts and are sagregated as condition based .eg C1, C2 and C3
CYCLE:
create refurbishment order- withdrawawal of spare parts from store- refurbishment execution- order completion confirmation- refurbished parts back to store- goods
receipt for returning

3. How to add the counter plan and strategy plan in a single maintenance plan?
multiple counter plan and stratergy plan cannot be added together, If u add counter plan with a stratergy, counter plan will be taken into cosideration ,stratergy will not be considered.

4. How can we assign measuring points to a strategy plan like compressor running hrs?
Go to the change equipment transaction , then extra, then add or replace counters. then select the desired counter by F4 help. you can't directly add counters or measuring pts to a maintenance plan.
You can do this for equipment ,FL and PRT only.

5. What is aMilestone Confirmation?
The milestone confirmation is a special form of confirmation, in which the confirmation of one operation causes other operations or suboperations to be automatically confirmed at the same time.
Milestones are operations that have the corresponding indicator in the control key.
Operations can be defined as milestone operations in their control keys. If a milestone operation is confirmed, then previous operations are automatically confirmed.